Jiangnan Shipyard plans to deliver 25 vessels of 12 types in 2025

On February 27, 2025, Jiangnan Shipyard is operating at full capacity with its dock fully engaged in production.

This year, Jiangnan Shipyard plans to deliver 25 ships of 12 different types, with the Mark III large LNG carriers being the key project. The first vessel is scheduled for completion in March. The shipbuilder aims to deliver LNG carrier every four months, maintaining a construction cycle of under 20 months.

Additionally, Jiangnan Shipyard plans to deliver five large container vessels, including the self-developed “Kun Series” methanol vessels, as well as nine large gas carriers.