Recently, at Qingdao International High-End Equipment Manufacturing Base of Offshore Oil Engineering Co., Ltd. (COOEC), the main structure of the S007 jacket for the Qatar ISND 5-2 project was successfully integrated, marking the completion of the topside installation for all jackets in the project.
The project, invested in and developed by QatarEnergy, is the most comprehensive and complex international offshore oil and gas field EPC (Engineering, Procurement, and Construction) project undertaken by Chinese enterprises. COOEC is responsible for the construction of three wellhead platforms, three jackets, and three subsea skids, as well as the modification of existing platforms, onshore prefabrication, and the fabrication of subsea Sleeper steel bridge structures.
It is reported that the capped S007 conduit rack is 24.5 meters long, 21.25 meters wide, 39.9 meters high and weighs 910.3 tons, and its construction difficulty and technical requirements have reached the international advanced level.
It is reported that the recently topped-out S007 jacket measures 24.5 meters in length, 21.25 meters in width, and 39.9 meters in height, with a weight of 910.3 tons. Both the construction difficulty and technical requirements of this jacket have reached internationally advanced levels.